Woody Creek 2007

  • Client: City of Grande Prairie
  • Consulting Firm: Bearisto, Lehners, Ketchum Eng. Ltd.
  • Cost of Project: $2.2 million
  • Location: Grande Prairie, Alberta
  • Date: May 2007-October 2007
  • Scope of Work: Built a 2600m canal drainage system along East side of Grande Prairie, which included: 370,000cu.m of excavation.  140,000sq.m of landscaping, 81.5m of horizontal directional boring.  3 control structures and 5 outfalls.

July27 059

Before

OLYMPUS DIGITAL CAMERA

OLYMPUS DIGITAL CAMERA

Completed Storm Water Management Canal