Drainage System, Woody Creek AB, 2007

  • Cost of Project: $2.2 million
  • Client: City of Grande Prairie
  • Consulting Firm: Bearisto, Lehners, Ketchum Eng. Ltd 
  • Project Details: Built a 2600m canal drainage system along the East side of Grande Prairie, which included: 370,000cu.m of excavation. 140,000sq.m of landscaping, 81.5m of horizontal directional boring.  There were 3 control structures and 5 outfalls.

July27 059

OLYMPUS DIGITAL CAMERA

Timeline: May to October