Well Construction & Access Upgrade, Wembley AB, 2024
19,000 cu.m of material was excavated on this 140m by 270m wellsite. An additional 300 m of access was built & padded using borrow pit material. The design for this build was created by Klassen Brothers and implemented using GPS equipment. February to March
-

Wellsite & Access Construction, East of Grande Prairie, 2024
104,000 m3 of material was excavated on this 200m by 280m wellsite. Included in this build was 1200m of access development. The design for this build was created by Klassen Brothers and implemented using GPS equipment. October to December
-

Wellsite & Access Construction, Saddle Hills AB, 2024
30,000 m3 of material was excavated on this 190m by 325m wellsite. The design for this build was created by Klassen Brothers and implemented using GPS equipment. November to December
-

Wellsite Extension, Wembley AB, 2024
13,000 m3 of material was excavated on this 140m by 190m wellsite. The design for this build was created by Klassen Brothers and implemented using GPS equipment. October to November