Cleardale 2008

-
Client: Alberta Infrastructure and Transportation
-
Consulting Firm: Thurber Engineering Ltd.
-
Cost of Project: $5 million
-
Date: February – September 5, 2008
-
Location: Cleardale, Alberta
-
Scope of Work: Klassen was awarded the Cleardale site in order to excavate 430,000cu.m of fill, stabilize 11 highway slides and provide drainage for existing slumps in order to stabilize 3 km of highway. The work required a complete Traffic Accommodation Plan, Storm Water Management Plan and ECO Plan.
Moving Fill Across Highway
OLYMPUS DIGITAL CAMERA
Before: Erosion on South side of Highway due to Outlet Failure
Redesigned Outlet Structure on Nouthside including Culvert Extension and Riprap
Boring New Culvert Under the Highway

OLYMPUS DIGITAL CAMERA
Before: Outlet Structure on Northside of Highway
Outlet Structure on Southside of Highway, Improved Drainage and Concrete Headwall
Project In Motion: April
Project in Motion: March