- Client: SemCAMS
- Consulting Firm: SemCAMS
- Cost of Project: $2 million
- Location: Fox Creek, Alberta
- Date: June 2008
-
Project Details: Sulphur Storage and Conveyor Demolition was a multi-bid project. Klassen was awarded the demolition and paving. We removed existing overhead and underground structures by salvaging the conveyor belts with cranes and dynamiting the concrete towers. After the soil was remediation, replaced, and concreted. Klassens paved 10,000m2.
Facility Before Demolition
Demolition
Cranes Removing Conveyors