Storm Water Pond, Edmonton AB, 2008

  • Client: City of Edmonton
  • Consulting Firm: ISL Engineering Ltd.
  • Cost of Project: $1.1 million
  • Date: April 17 – July 1, 2008
  • Location: Edmonton, Alberta
  • Project Details: Tweddle Place is a residential community on the East side of Edmonton that required a Storm Water Management Pond.  27,000cu.m of fill was removed from the site next to Whitemud Drive.  Construction included the designing and implementation of a Traffic accommodation plan to coordinate fill removal and congested city streets.  Drainage for the pond was tied into the City sewer system with outlet structures and various underground facilities, which required an ECO plan and erosion control measures.  Soil stability measures were implemented for two months.

IMG_0276

Before

IMG_0370

Loading Trucks in Rush Hour

AAc 059

First Cut

OLYMPUS DIGITAL CAMERA
OLYMPUS DIGITAL CAMERA

Completed Site