multi-plate Blue Ridge ab, 2009

Completed Multi-plate with Erosion Control
· Client: Alberta Transportation
· Consulting Firm: MPA Engineering Ltd.
· Cost of Project: $1.15 million.
· Location: Blue Ridge, Alberta.
· Date: July – October 2009
· Scope of Work: Removal of existing multi-plate structure in Tributary of Bull Creek, a fish bearing stream. Replace multi-plate bridge with new multi-plate and back fill. Traffic Accommodation Plan, Storm Water Management Plan & ECO Plan were completed. Due to the in stream nature of this project a fish capture and release was completed before the in stream work started.

OLYMPUS DIGITAL CAMERA
Before Picture (East side of Bull Creek)

OLYMPUS DIGITAL CAMERA
Fish Capture

OLYMPUS DIGITAL CAMERA
Completed Detour
Covering Multi-plate
Paving Completed