Project Details: This reservoir was supposed to be built in July but kept getting pushed back until September due to continuing rain. The location was in an old cutblock and the topsoil was much deeper that expected and coupled with the moisture, it made the strippings the most difficult part of this project. The total excavation of the reservoir was 45,000m3.