Victor Lake, AB – Summer 2020

Date: August 2020

Client: MD of Greenview No.16

Consulting Firm: Teckera Civil Engineering Consultants

Project Details: This project upgraded roughly 3.2km of existing road. A combination of common and Contractor supplied borrow was required for a total of 41,000m3 of material. 191 meters of new culverts were installed and 2500 ton of new surface gravel was placed.

DCIM\100MEDIA\DJI_0121.JPG
DCIM\100MEDIA\DJI_0060.JPG
DCIM\100MEDIA\DJI_0065.JPG
DCIM\100MEDIA\DJI_0073.JPG
DCIM\100MEDIA\DJI_0069.JPG
DCIM\100MEDIA\DJI_0158.JPG